Decoating Furnace Emission and Permit Checklist for UBC and Coated Scrap
A decoating furnace is a permit question as much as a machine question. Fix the coating chemistry, feed form, hourly throughput, target burn loss and emission basis before quotation, and the furnace and off-gas system can be specified as one route.
Used beverage can decoating and coated aluminium scrap decoating both release coating volatiles. The furnace is therefore specified with its off-gas system and the site permit, not as an isolated kiln. This checklist turns the permit conversation into a fixed set of inputs a buyer can send to every supplier.
Why the permit belongs in the first enquiry
Coating removal happens before melting because it protects metal yield and keeps the melt furnace cleaner. In a UBC furnace the volatilised coating can be recirculated as fuel and the remainder treated, while in a delamination route the polymer is gasified under oxygen-free conditions and the resulting fuel gas can offset process energy. Both routes produce an off-gas stream that must fit the site permit, so the permit is not a final step; it sets the interface that the furnace and gas cleaning must meet.
Five inputs to fix before quotation
| Input | Why it matters | What to state |
|---|---|---|
| Coating chemistry | Halogenated or heavily loaded coatings change the off-gas duty | Paint, lacquer or laminate type and whether halogenated content is expected |
| Feed form | UBC, coated scrap, chips or composite each behave differently | Bulk density, arrival form and contamination |
| Hourly throughput | The off-gas system is sized for the real feed rate | Sustained tonnes per hour or batch size and cycle |
| Target burn loss | The metal yield target sets the process severity | The residual limit the melt furnace can accept |
| Emission basis | The site permit determines the final gas-cleaning interfaces | Dioxin, particulate and thermal oxidation requirements, including TA-Luft where applicable |
The permit checklist
- Name the coating chemistry and whether the feed may contain halogenated coatings
- Describe the feed form and contamination, not only the total volume
- State the sustained hourly throughput and operating hours
- Set the target burn loss or residual coating limit the melt furnace accepts
- Confirm the site emission basis, including TA-Luft where the site is in Germany
- Ask the supplier to state which gas-cleaning stages sit inside the equipment scope
- Require the quotation to make the equipment and site utility boundaries explicit
What a complete bid states
A complete bid states the furnace, the volatile recirculation scope, the thermal oxidation duty and the downstream gas cleaning together with the site interfaces. The published thermal process emission basis includes dioxins below 0.1 ng-TEQ per cubic metre, particulate below 10 mg per cubic metre, a thermal oxidizer at 850 C with a two-second residence time, and gas cleaning through quench, dual alkali scrubbing, activated carbon and a baghouse. The buyer's permit determines the final interfaces, so these figures are a design starting point rather than a fixed guarantee for every site.
Asking suppliers to quote against this same list exposes bids that quietly drop the off-gas or permit interface. The furnace and its gas handling are one system, and splitting them across suppliers leaves the interfaces to be resolved on site, where changes cost the most.
Decoating furnace permit FAQ
Do I need a permit conversation before I choose a furnace?
Yes. Decoating releases coating volatiles, so the off-gas system must fit the site permit. Fixing the emission basis before quotation keeps the furnace from being specified in a way the site cannot legally operate.
Does YUSHUNXIN issue the site permit conclusion?
No. We state the equipment scope and the emission interfaces, but the permit and the final compliance conclusion remain with the operator and its advisers.
Which inputs matter most for a first quote?
Coating chemistry, feed form, throughput, target burn loss and the site emission basis. With those five, the furnace size, energy recovery scope and gas-cleaning interfaces can be confirmed together.
Related reading
Decoating Furnace: Procurement Guide
The buyer types and purchase criteria behind a decoating furnace decision.
Safety & Emissions Engineering
How off-gas, dust and thermal oxidation are engineered into the route.
Aluminium Decoating: Energy and Emissions
Why decoating wins and how the energy loop and emission basis are engineered.