+86 182 0399 3035 [email protected] WhatsAppRequest a proposal

UAE - UBC Aluminium Decoating Furnace

A continuous decoating furnace that recirculates volatilised paint off-gas to reach self-sustaining thermal operation and cut remelting melt loss.

This reference shows a UBC decoating furnace installed in the Middle East. The furnace removes lacquer and coatings from used beverage cans before melting, recirculating the volatilised paint off-gas so the decoating stage runs with minimal external energy.

Project facts
RegionUAE / Middle East
ApplicationUBC aluminium can scrap decoating
ResultSmelting melt loss reduced by over 80%
EnergyPaint off-gas recirculation for self-sustaining operation

Scope: one continuous decoating furnace

The project was scoped as a continuous decoating stage feeding an existing melt operation. The design basis was fixed around the shredded UBC feed, the lacquer load and the melt capacity, so the furnace delivers clean metal at the rate the melting stage accepts. Scoping the decoater and the melt interface together is what makes the result transferable: the furnace was not sold as a standalone box but as the stage that protects the melt.

UBC decoating furnace drum
The furnace is scoped as the stage that protects the existing melt operation.

UBC feed and Gulf conditions

Shredded UBC arrives with lacquer, printed films and some moisture, and the furnace is set for that feed rather than a perfect dry stream. In a hot Middle East climate the material can arrive warm and dry, which changes the energy balance and the handling, and the furnace design accounts for the local utility and ambient conditions. The melt shop's available capacity and craneage were confirmed before the interface was drawn.

Shredded UBC feed conveyor
The furnace is set for the real shredded UBC feed and local site conditions.

Decoating, off-gas and melt transfer

Shredded cans are metered into a continuous rotating drum with internal flights, where the lacquer and coatings are removed under controlled low-oxygen heating. The volatilised coating is recirculated and the remainder treated, while the clean metal is transferred to the melting stage. The key equipment is the drum furnace itself, supported by the feeding, off-gas and melt transfer stages that keep the line continuous.

Continuous rotary decoating drum
A rotating drum with internal flights keeps the charge and coating exposure even.

Energy recovery from paint off-gas

The distinctive feature of this reference is the energy loop. The volatilised paint off-gas is recirculated as a fuel stream, so the decoating stage can run self-sustaining with minimal external energy once the coating is burning. This turns the coating from a disposal problem into an energy source, which is why the furnace economics are better than a simple heated kiln that vents the volatiles.

UBC decoating energy recovery loop
Paint off-gas recirculation turns coating into fuel for self-sustaining operation.

Compliance and emission basis

Decoating releases coating volatiles, so the off-gas system is sized with the furnace and the local emission basis. The published thermal process emission basis, including thermal oxidation and downstream gas cleaning, frames the design, and the recirculation loop reduces the volume that must be treated. The buyer's permit determines the final interfaces, which are confirmed during specification rather than after the furnace is installed.

Decoating off-gas and melt shop interface
The off-gas route is sized with the furnace and the site permit.

Manufacture and shipping

The furnace was manufactured and tested within the fast manufacturing window used across the thermal equipment board. The drum, flights and refractory were built and inspected before dispatch, and the control and burner systems were selected for the local supply. Shipping and installation were planned so the furnace arrived in a sequence that matched the melt shop's shutdown and assembly windows.

Aluminium ingot casting after decoating
The furnace is delivered in a sequence that matches the melt shop's windows.

Burner and control automation

The furnace runs on the standard automation platform, with the motor voltages matched to the site and the control scope covering feed rate, drum speed, temperature and the off-gas loop from one interface. Integrating the decoater into the melt shop's control view lets operators balance the two stages, which is exactly what prevents the decoater from outrunning or starving the melt furnace.

Decoating furnace control integration
One control view balances feed, drum, temperature and the melt stage.

Installation and commissioning on site

Commissioning followed the delivery sequence and ended with continuous testing on real UBC. Running the furnace against the actual feed proves the decoating performance, the energy recovery loop and the transfer of clean metal to the melt. This is where the recirculation balance is tuned, because the paint load of the real feed is what determines how much external energy the furnace still needs.

UBC decoating commissioning with real cans
Real UBC feed is the proof of decoating and energy recovery performance.

The operator's result

The operator gained a decoating stage that reduces smelting melt loss by over 80% by removing the coating before the metal enters the melt, and a furnace that recirculates paint off-gas to run near self-sustaining. The result is more saleable aluminium from the same UBC feed and a melt furnace that runs cleaner with fewer dross interruptions, which is the point of decoating in the first place.

Clean metal entering the melt shop
Clean metal enters the melt, cutting melt loss and dross interruptions.

Lessons that transfer to similar decoating projects

Three lessons transfer. First, size the decoater and the melt interface together, because the two stages have to balance. Second, treat the coating off-gas as an energy stream where the paint load allows it, rather than a disposal problem. Third, commission on the real feed, because the energy recovery balance depends on the actual lacquer load and cannot be confirmed from a dry test.

Decoating project lessons
Melt interface, off-gas energy and real feed define a successful decoater.

Scoping a comparable decoating project

Send the UBC feed description, the lacquer type and load, the hourly throughput and your melt capacity. We will confirm the drum duty, the temperature and atmosphere profile, the off-gas recirculation balance and the melt transfer interface. That gives you a scope comparable to this reference, with the energy recovery benefit stated against your actual coating load rather than borrowed from another plant.

Scoping a comparable UBC decoating project
Feed, lacquer load, throughput and melt capacity define a comparable scope.

UAE UBC decoating furnace FAQ

How is the melt loss reduction measured?

The reference states a smelting melt loss reduction of over 80%, which means the metal lost to dross when coatings burn inside the melt is cut by removing the coating first. The furnace's own confirmed specification is below 0.5% metal burn loss in decoating, and the downstream melt result depends on the melt furnace and feed.

For a comparable project the number is calculated against your actual feed and melt operation, not borrowed from this reference. We state the decoating performance we confirm and let the melt loss be derived on your basis, so the figure stays honest.

If you want to verify the benefit, send your current melt loss baseline and feed description. We will show where the reduction comes from and which part is decoating performance versus melt furnace behaviour.

Comparing decoating performance and melt furnace behaviour separately keeps the benefit honest. The decoater removes the coating and states its own burn loss, while the melt loss reduction is calculated on your furnace and feed, so the claimed improvement is tied to a basis you can check.

Separating the two also changes how you audit the claim. You can check the decoater's burn loss against a defined feed, and you can check the melt loss reduction against your own furnace data, but you cannot check a single blended number that mixes both. Asking for the split is the first step in any honest verification.

The split also matters when the numbers disagree. If the decoating performance is confirmed but the melt loss result is not, the two facts must be evaluated separately, and the cause of the difference will be found in the melt furnace or the feed, not in the decoater. Blending them hides exactly the information you need to find the problem.

The split is what makes each number meaningful, because a figure without its basis cannot be checked.

What makes the furnace self-sustaining?

The volatilised paint off-gas is recirculated as a fuel stream rather than vented, so the energy released by the coating offsets the heat the furnace needs. Once the coating is burning, the external energy demand drops sharply, which is what makes the operation close to self-sustaining.

The exact balance depends on the lacquer load and throughput of the real feed, which is why the recirculation loop is tuned during commissioning on actual UBC rather than set from a brochure.

Self-sustaining does not mean no energy is ever needed. Start-up still requires external heat, and a low-coating feed may need more support. The benefit is real but it is stated against the actual coating load.

The recirculation loop also reduces the volume of off-gas that must be treated, which matters where emission limits are tight. The energy benefit and the emission benefit come from the same design decision, which is why the loop is sized with the furnace and the permit together.

The permit interface benefits from the same decision. Recirculating the off-gas changes the volume and composition of what remains to be treated, so the gas-cleaning duty and the permit are set together. A furnace designed without the loop would need a different off-gas scope, which is why the energy and emission questions are one question.

That is also why the recirculation loop is not an aftermarket add-on. It changes the gas flows, the burner duty and the control logic, so adding it later means reworking the furnace rather than connecting a part. Designing the loop in from the start is the only way to get both the energy benefit and the emission benefit together.

The loop and the furnace are one design, not two purchases, and the permit is written around that single design. Treating them as one is what makes the energy claim real.

Will this furnace fit my existing melt shop?

The furnace is scoped around the melt interface, so the question is whether your feed, lacquer load and melt capacity match the continuous duty. We confirm the available space, craneage, power and the melt furnace's feed arrangement before drawing the interface.

A decoater that outpaces the melt furnace just moves the bottleneck downstream, so we size the drum duty to your melt capacity rather than selling a standalone capacity number.

Send the UBC feed description, throughput and melt capacity. We will confirm the furnace footprint, the transfer arrangement and whether the off-gas and permit interfaces fit your site.

The transfer arrangement matters as much as the furnace footprint. Clean hot metal must arrive at the melt furnace in a form it can accept, at the right temperature and rate, so the two stages are sized together rather than as separate purchases.

The transfer arrangement also affects safety and downtime. Hot metal that arrives at the wrong rate or temperature causes bridging, spills or furnace upsets, and each one costs production. Sizing the transfer with the melt furnace turns the decoater into a reliable feed source instead of a bottleneck that the melt shop works around.

The interface also decides how the two stages are controlled together. If the decoater and the melt furnace do not share a feed-rate signal, the operator has to balance them by hand, and the system drifts out of step. Integrating the control at the transfer point is what keeps a continuous decoating and melting line actually continuous.

Shared control at the transfer point is what keeps the two stages running as one system instead of drifting apart, and it is decided before the furnace is built. Fixing the interface early is what keeps a continuous melt shop genuinely continuous, day after day, every single shift.

The reference also shows why the melt interface is part of the decoater specification. A furnace that delivers clean metal at the wrong temperature or rate simply moves the problem into the melt shop, so feeding, drum duty and transfer are sized together. Buyers who treat the decoater as a standalone box usually find the savings disappear in the interface work that follows.

Finally, the energy claim is stated against the coating load for a reason. Paint off-gas recirculation is real, but its benefit scales with the lacquer in the feed, so a plant with a light coating load should expect a different balance than this reference. Asking for the balance on your own feed is the only way to turn the claim into a number you can plan around. The same principle applies to the melt loss figure: it is calculated from your feed and your melt furnace, not borrowed from this project, because a decoater can only remove the coating and the furnace then decides the rest. A buyer who understands that split can verify every claim against a stated basis, and a buyer who does not is left comparing numbers that were measured under different conditions. When you send the feed and melt capacity, we return the energy and melt loss basis for your plant, with the assumptions written next to each figure, so every number you plan around has its basis attached. Take the reference as a system story, not a furnace price: feeding, decoating, energy recovery and melt transfer only work when they are sized together, and the energy and melt loss evidence only holds up when it is stated against the actual feed and melt furnace.

Verifying a decoating furnace claim

How do I verify the energy and melt-loss claims before buying a decoater?

Separate the decoating performance from the melt furnace result. The decoater's own burn loss is stated against its feed, while the melt loss reduction depends on the downstream furnace and the coating load, so the two figures should not be quoted as one universal number.

Ask for the energy balance against your coating load. A furnace that recirculates paint off-gas approaches self-sustaining operation where the coating is heavy, but start-up still needs external heat and a light coating load needs more support. The balance must be calculated on your feed, not borrowed from another plant.

Ask how the off-gas and permit interfaces are handled. The recirculation loop reduces the volume to be treated, but the remaining stream still has to meet the site's emission basis, and that basis determines the final gas-cleaning scope.

Finally, ask for a continuous test on real UBC. The energy recovery and decoating performance only become visible when the actual lacquer load runs through the furnace, so a dry test or a brochure figure is not the same evidence as a commissioning run on your feed.

A continuous test on your own feed is the strongest form of that evidence. It shows the decoating quality, the energy recovery and the off-gas performance at the same time, on the material the furnace will actually process. Accepting a dry test or a reference figure in place of that is accepting a promise instead of a proof.

The test also sets the operating baseline for the future. The temperatures, feed rates and off-gas readings recorded during the test become the reference point for later performance, so the operator knows when the furnace drifts and when it needs attention. A plant without that baseline is running blind from its first day.

The baseline is the first asset the test produces, and it lasts for the life of the plant.

WhatsApp
Call WhatsApp Get a quote