European Permit and Utility Readiness Map for Recycling and Decoating Lines

PV, battery and decoating projects share one preparation discipline: fix the permit, utility and site interfaces before the line. This map shows what to prepare for each board and how to make the bids comparable.

A recycling or decoating line is easier to buy when the site is ready. This map groups the permit, utility and interface questions by board, so a project team can prepare the same inputs for every supplier and avoid rework after the order.

Why readiness comes before quotation

Equipment specifications depend on the power, dust, fire and off-gas interfaces the site can accept. When those are unknown, suppliers quote against different assumptions and the differences surface only during installation. Fixing readiness first turns the project into a repeatable procurement exercise.

The three-board readiness map

Readiness itemPV recyclingBattery recyclingDecoating furnace
Permit and frameworkWEEE 2012/19/EU; TA-Luft where a thermal route appliesEU Battery Regulation 2023/1542Local emission permit; TA-Luft where applicable
Site interfaceModule storage, dust and thermal off-gasDischarge, inerting, dust and fire interfacesCoating volatile handling and furnace off-gas
Utility basisPower and dust extraction for the selected routeNitrogen supply and the site voltage basisFuel or energy recovery and gas-cleaning utilities
First-enquiry inputModule mix, glass construction and damage shareChemistry, format, condition and state of chargeFeed, coating load, throughput and target burn loss
Supplier boundaryEquipment scope versus site permit and utilitiesDischarge to separation train versus site fire systemFurnace and gas cleaning versus site utilities

A readiness checklist for every board

  • State the applicable framework and site permit
  • Describe the feed, condition and contamination
  • Confirm the site power, dust, fire and off-gas interfaces
  • Confirm the voltage basis and the DCS or SCADA interface
  • Require every supplier to state the equipment and site boundary
  • Make the accepted quotation document the acceptance test

The published thermal process emission basis gives a starting point for the permit conversation: dioxins below 0.1 ng-TEQ per cubic metre, particulate below 10 mg per cubic metre, a thermal oxidizer at 850 C with a two-second residence time, and gas cleaning through quench, dual alkali scrubbing, activated carbon and a baghouse. The buyer's permit determines the final interfaces, so the figures are a design basis rather than a fixed guarantee for every site.

Permit and utility readiness FAQ

Which readiness item is missed most often?

The fire and off-gas boundary. A battery line needs its dust and fire interfaces to sit inside the wider site strategy, while a decoating furnace needs its gas cleaning sized with the permit. Fixing both before quotation is cheaper than reconciling them after delivery.

Can I use the same readiness checklist for all three boards?

Yes. The feed and framework differ, but the request is the same: state the permit, utilities and interfaces, then require every supplier to quote on that basis.

Does YUSHUNXIN prepare the site permit?

No. We state the equipment scope and the interfaces, while the permit and the final compliance conclusion stay with the operator and its advisers.